A delivered extraction system is not yet a producing one. Between the crates arriving and the first batch of botanical material going in, your project has to clear several gates: approvals, acceptance testing, pressure and leak testing, a full check of the safety layer and an operator handoff. This guide covers extraction equipment installation and commissioning in the order the work happens. For each step it shows who leads, what gets checked and what record it leaves behind. Those records are what your fire code official, your engineer of record and your quality team will ask to see.
What installation and commissioning mean for a solvent extraction system
Installation puts the system in place and connects it to the room's utilities as drawn. Commissioning proves, with a written record, that the installed system runs, alarms and shuts down as designed before any production material goes in.
Our extraction lab equipment overview covers the install sequence in a short passage. This article goes deeper on the sequence and the documents each step produces.
Installation: setting, anchoring and connecting the system to the room
Installation is mechanical work. The skids are rigged into the room, set, leveled and anchored. They are then connected to power, chilled fluid, compressed air, nitrogen, exhaust and controls at the points shown on the equipment drawings. The output is an as-installed check confirming that what is in the room matches what is on paper.
Commissioning: proving with documented evidence that it runs as designed
Commissioning is evidence. Every instrument, alarm, interlock and shutdown gets exercised, and every result gets written down and signed.
Regulated plants use a shared vocabulary for that evidence. CASRAI describes IQ/OQ/PQ as a three-stage documented sequence with a distinct purpose at each stage:
- Installation qualification proves the system was installed correctly.
- Operational qualification proves it operates correctly across its specified range.
- Performance qualification proves it performs consistently under actual conditions of use.
Not every operation runs formal qualification, but the logic holds on every install. Check the install, check the function, then check the performance.
Why a delivered system is not yet an approved system
Your extraction process needs approval from your Authority Having Jurisdiction (AHJ) before it runs, and the equipment is part of that approval. The International Fire Code chapter on processing and extraction facilities addresses this directly. Where the fire code official requires it, the engineer of record inspects the installed extraction equipment before operation and reports findings before the extraction process is approved. That field report includes the equipment serial number and confirms that the model and type match the technical report.
That requirement is why commissioning ends with a sign-off and not just a test run that looked good. Engineered controls reduce hazards. Commissioning documents that each control was installed and verified to operate as designed.
Approvals that have to be in place before the equipment ships
Approvals set the installation schedule more than freight does, so settle them before the system leaves the build floor.
Listed equipment vs. equipment reviewed through a technical report
The International Code Council's International Fire Code gives extraction equipment two approval paths. The equipment is either listed and labeled to UL 1389, or approved for the specific use after a registered design professional reviews it and documents the review in a technical report. Confirm with your AHJ which path your system takes and which code edition your jurisdiction has adopted, and do it before the purchase order is final. Some jurisdictions enforce NFPA 1 instead of the IFC, so confirm the governing document as well.
Why the technical report comes before the equipment is placed
The same code requires the approved technical report before the equipment is located or installed at the facility. A late report therefore holds up the whole install, because the system cannot be set in the room until the review is complete.
A turnkey system still goes through local approval. Equipment documentation supports the permit. It does not replace it.
Solvent choice, model and serial number: what the approval is tied to
The technical-report path approves equipment for a specific use, so the approval is tied to the configuration that was reviewed. The engineer of record's field report has to record the serial number and confirm the installed unit is the same model and type the technical report describes. In practice, that means two things:
- Lock the solvent, model and configuration before submittal.
- Don't accept a substitute unit late in the project.
Changes after approval also matter. Oklahoma City Fire Department policy states that modifying the equipment or relocating it to a new address voids the equipment approval. Rules vary by jurisdiction, but the general principle holds: any change made after approval goes back through your AHJ.
Documentation to request from the manufacturer up front
Your engineer of record and AHJ will work from the manufacturer's documents. Request this package before shipment:
- Piping and instrumentation diagrams (P&IDs)
- Operating and maintenance manuals
- Pressure vessel documentation (see ASME pressure equipment for extraction systems)
- Control panel documentation (see UL 508A control panels)
- Bill of materials
- Emergency procedures
MACH equipment carries the CE, IECEx, UL 508A, PSI and ASME compliance marks. Our breakdown of what each compliance mark covers explains the scope of each one.
Extraction equipment must be installed, permitted, and operated in accordance with all applicable federal, state, and local fire, building, and electrical codes, including Class I Division 1 requirements where applicable. Consult your Authority Having Jurisdiction (AHJ) before installation.
Factory acceptance testing: find problems before the system leaves the build floor
A factory acceptance test (FAT) is testing done at the manufacturer's facility, before shipment, to confirm the system meets the agreed specification. PQE Group summarizes ISPE Baseline Guide Volume 5 on this point: after FAT, the owner and vendor agree whether the system is ready to ship.
What a factory acceptance test (FAT) covers on an extraction skid
PQE Group lists the FAT/SAT scope as P&ID verification, instrument calibration verification, I/O verification, alarms, interlocks and control panel verification. On an automated extraction skid, each item maps to hardware you can point at:
- P&ID verification: every vessel, valve, pump and line on the skid matches the drawing.
- Calibration checks: pressure transducers, temperature probes and level sensors read correctly against a reference.
- I/O checks: each signal lands on the right controller channel, and each output drives the right solvent pump, valve or heater.
- Alarms and interlocks: high-pressure, high-temperature and high-level conditions trigger the response they are programmed for.
- Control panel functions: recovery controls, process steps and shutdown sequences behave as specified.
These checks apply to our EES Series automated ethanol extraction systems and our AHES Series hydrocarbon extraction systems alike. The instrument list differs by solvent, but the method is the same.
Why fixing faults at the factory costs less than fixing them on site
Lab Manager notes that correcting a control configuration error at FAT costs a fraction of correcting it after installation.
The reasons are practical. At the factory, the engineers who wrote the control logic, the spare components and the test equipment are all on the same floor. On site, the same fix has to wait on travel, on access to a classified room and on a construction schedule that is already moving.
How factory records cut down on-site testing
The same Lab Manager guide points out that FAT can reduce the scope of site IQ. With accepted factory records in hand, site work can concentrate on what only the site can show: utilities, field wiring and the room itself.
Every MACH system is designed, fabricated, assembled and tested in our vertically integrated Michigan facility. Whichever manufacturer you are evaluating, ask which factory test records ship with the system and whether a factory test can be witnessed.
Site readiness: what the room needs before the crates arrive
An install can stall in the room just as easily as at the equipment. Confirm the items below before delivery. For the detail behind each one, see our guides on sizing utilities for an extraction lab and what a C1D1 room requires.
Rigging path, floor loading and service clearances
- Door widths, corridor turns and the freight path from the dock to the room
- Slab capacity under the loaded skids, calculated with the vessels full
- Service access around every skid for maintenance and inspection
- Floor coatings and sealants fully hardened before any equipment is set
Utility rough-ins: power, chilled fluid, compressed air, nitrogen
Each utility should be roughed in and terminated to the equipment drawings before the skids arrive. That covers:
- Power at the specified voltage and capacity
- Chilled fluid supply and return
- Compressed air for pneumatic actuators
- Nitrogen for purging and leak testing
A rough-in a few feet off the drawing turns into field rework during hookup.
Exhaust and gas detection running before solvent comes in
The International Fire Code requires continuous mechanical exhaust of not less than 5 cfm per square foot of floor area to keep flammable vapors below 25 percent of the lower explosive limit (LEL). Commissioning should measure the installed exhaust against the design value instead of assuming the fan schedule was met.
The same chapter requires gas detection where extraction uses flammable-gas solvents. Continuous gas detection should be powered, calibrated and reporting before any solvent enters the room. It should not be a last-minute item during hookup.
Classified electrical finished and inspected
Classified-area electrical work has to be finished and inspected before the extraction equipment is connected. Where the process requires it, that means devices and wiring rated for Class I, Division 1 locations. If the enclosure decision is still open, start with which classification your process triggers. Then review our comparison of a prefabricated booth vs field-built classified room.
Extraction equipment installation and commissioning, step by step
Each phase has an owner, a set of checks and a record. The table below is the backbone of the process. The subsections that follow expand the phases that carry the most detail.
The milestone table: phase, who leads, what is checked, what record it produces
| Phase | Who leads | What is checked | Record produced |
|---|---|---|---|
| 1. Approvals in hand | Owner and engineer of record | Approval path settled; technical report reviewed and approved | Approved technical report |
| 2. Factory acceptance | Manufacturer, with owner agreement | P&IDs, calibration, I/O, alarms, interlocks, control panel | FAT record and punch list |
| 3. Receiving | Owner | Packing list, shipping damage, serial number and model against purchase order and technical report | Receiving inspection record |
| 4. Setting and utility hookup | Owner's contractors, with manufacturer guidance | Placement, anchoring and utility connections against drawings | As-installed check |
| 5. Pressure/vacuum and leak testing | Per the manufacturer's procedure | Closed-loop integrity with inert gas; vacuum integrity on recovery | Leak test record |
| 6. Loop checks and interlock tests (SAT) | Owner's team, with manufacturer support | Each field device to controller; cause-and-effect responses | Loop check sheets and interlock test record |
| 7. Gas detection and exhaust | Owner's team | Alarm and fault (trouble) response; exhaust airflow against design, at least 5 cfm/ft² under the model IFC | Test record |
| 8. Engineer of record field inspection | Engineer of record, where the fire code official requires it | Installed equipment, serial number, model and type against the technical report | Field inspection report |
| 9. Solvent charge and solvent-only runs | Owner's operators, with manufacturer guidance | Fill, circulation, recovery and shutdown with no plant material | Run log |
| 10. First material runs and handoff | Owner's operators and trainer | Production on representative feedstock; operator demonstrations | Training record and handoff sign-off |
Receiving and inspection
Receiving is the first quality check on site. GetReskilled lists three installation checks: verify received items against the packing list, inspect for shipping damage, and verify serial numbers, make and model.
On an extraction project, the serial check carries extra weight. The engineer of record's field report has to match that serial number to the technical report, so catch any mismatch at the dock rather than at the inspection.
Mechanical completion and punch list
Mechanical completion means the system is set, connected and ready for testing. Any open items go on the punch list. Tagsight notes that FAT punch items carry into SAT and are closed before acceptance. Items logged at the factory and new findings from the site therefore end up on one list, and that list is cleared before the system is accepted.
Solvent charge, solvent-only runs and first production run
No production material goes in until the safety layer has been tested and the approvals are signed off.
Solvent comes next. The system is charged and run on solvent alone to confirm that fill, circulation, recovery and shutdown behave the way the earlier tests predicted. Only after the solvent-only runs does the first botanical material go in. Trained operators should be at the controls, and the run is documented as part of the handoff.
Pressure, vacuum and leak testing before any solvent goes in
Leak testing proves the system holds pressure or vacuum before anything flammable enters it. The method depends on the solvent.
Hydrocarbon systems: proving the closed loop holds
A hydrocarbon closed-loop system is leak-tested with inert gas after mechanical completion and before any hydrocarbon is introduced. MCCS International describes nitrogen/helium leak testing in exactly that window and notes that test pressure should never exceed the equipment's rated pressure.
On AHES Series automated systems and MHES Series operator-driven systems alike, the test pressure is set by two things: the manufacturer's procedure and each vessel's rating. It is never set by a field rule of thumb. The test should cover every joint from the solvent tank through the collection vessel.
For pressure ratings and recovery design, see the closed loop extraction system specification. For system options, see our hydrocarbon extraction equipment page.
Ethanol systems: vacuum integrity on recovery and evaporation
Ethanol systems such as the EES Series and M Series run solvent recovery at reduced pressure. Commissioning therefore focuses on vacuum integrity across recovery and evaporation. A vacuum leak raises the pressure the recovery stage runs at, which pulls the whole recovery curve away from its design point.
The physics are covered in our pages on ethanol's boiling curve under vacuum and solvent recovery in botanical processing. For full system options, see our ethanol extraction systems.
Why nitrogen is the usual test gas
Nitrogen is inert, so pressurizing a closed loop with it adds no fuel to the system. N2 Solutions notes that, unlike hydrotesting, nitrogen requires no extensive drying afterward. That matters on equipment that has to be dry before solvent goes in. Some projects also add a helium tracer to the nitrogen so a detector can locate small leaks.
Proving the safety layer: interlocks, gas detection and emergency shutoff
Factory testing proves the logic. Site testing proves that logic works with the real devices, the real wiring and the real room.
Site acceptance testing and loop checks
A site acceptance test (SAT) checks the installed system against real field signals. Tagsight describes SAT as verifying the installed system with loop checks, and notes that IEC 62381 defines FAT, SAT and site integration tests for process automation.
A loop check traces each instrument from the field device to the controller display. The SAT then confirms the installed system behaves the way FAT predicted.
Kneat adds that SAT repeats interlock tests under site conditions and verifies relief valves, emergency stops and door interlocks in the installed configuration. A cause-and-effect matrix maps each input condition to the actions it should trigger. It gives the test team a checklist they can sign off line by line.
What gas detection must do when it fails
When the gas detection system fails, the International Fire Code requires three responses:
- Deactivate the heating system.
- Activate mechanical ventilation where it is interlocked with gas detection.
- Initiate a trouble signal.
Commissioning should test both the gas alarm and the detector-failure response. A system that alarms correctly but does nothing when a sensor drops offline has passed only half the test.
Emergency stops and shutoff on hydrocarbon systems
The same chapter requires emergency shutoff systems where extraction uses gaseous hydrocarbon solvents. Commissioning should operate each shutoff in the installed setup. It should also record that every valve, pump and heater responds the way the cause-and-effect matrix says it should.
Control panel documentation
The control panel is where the interlock logic lives, so its documentation belongs in the commissioning file. That includes wiring diagrams, I/O lists and the as-tested program version. MACH systems carry the UL 508A mark. For what that mark covers on an extraction system, see our page on UL 508A control panels for extraction systems.
When the project needs IQ, OQ and PQ documentation
Not every extraction lab runs formal qualification. Operations working under GMP expectations, including nutraceutical and natural-products extraction, typically do. If that describes your operation, our guide to designing for GMP extraction covers the facility side.
Who needs formal qualification: GMP operations and nutraceutical lines
The amount of qualification follows the equipment's impact on product. Lab Manager explains that direct-impact equipment requires full qualification, while indirect-impact equipment may need only commissioning verification.
In an extraction lab, the split usually looks like this:
- Direct impact: extraction vessels, recovery and post-processing equipment that touch product.
- Indirect impact: chillers, compressed air and other supporting utilities.
Your quality team may structure the program under ISPE Baseline Guide 5 or ASTM E2500. Which framework applies is their call.
Acceptance criteria written before testing
Qualification needs acceptance criteria written before testing starts. CASRAI notes that a user requirements specification (URS) approved before purchase does two things. It gives the operation something to qualify against, and it lets vendor IQ/OQ support be negotiated into the purchase. Write the URS while you are still comparing systems, not after the skid is anchored.
Reusing factory and site test records
Good acceptance testing pays off twice. Kneat notes that a thorough SAT generates baseline evidence that streamlines IQ and OQ. Web of Pharma notes that IQ and OQ may be combined when the choice is risk-justified. A simple system with clean FAT and SAT records is the natural candidate for combining them.
Where performance qualification ends and process validation begins
Performance qualification shows the equipment performs consistently on representative feedstock. Process validation is a separate exercise, and Web of Pharma is explicit that PQ and process validation are not interchangeable. There is also no universal PQ run count, so the protocol has to justify the number of runs it uses.
Throughput, yield, purity, and solvent recovery figures vary with input material, system configuration, and process parameters. Published figures are not a guarantee of results.
Operator training and handoff: when commissioning is actually finished
Commissioning is finished when trained operators can run, shut down and recover the system on their own. Tightening the last fitting does not end it.
Train during commissioning, not after
Operator training belongs inside commissioning. Operators who watch the leak tests, loop checks and solvent-only runs learn the system's normal behavior and alarm responses on the same equipment they will run in production. MACH's service offering includes installation, training and on-demand technical support. See installation, training and technical support for current options.
What operators must be able to show before sign-off
Before handoff, each operator should be able to demonstrate:
- Normal operation, from startup through solvent recovery
- Emergency shutdown
- Alarm response, including gas detection alarms and trouble signals
- Routine maintenance
- Basic troubleshooting
Record each demonstration in the training record. That record closes out the commissioning file.
Changes after approval: solvent, configuration, location
An approval covers the system as it was reviewed. Changing the solvent, modifying the equipment or moving it can send the system back through review. Oklahoma City Fire Department policy, for example, says modification or relocation to a new address voids the equipment approval. Check with your AHJ before making any change, however small it looks.
Operators are responsible for verifying that their intended use is lawful in their jurisdiction.
Questions to settle with your equipment manufacturer before install day
Responsibilities that are written down before the crates ship don't have to be negotiated on install day. Take these questions into your next vendor meeting.
Documentation and approval support
- Is the equipment listed and labeled to UL 1389, or will it go through a technical report?
- Which documents ship with the system: P&IDs, manuals, pressure vessel and control panel documentation, bill of materials, emergency procedures?
- What equipment data will be available to your engineer of record for the technical report?
Factory testing and records
- Which factory test records ship with the system?
- Can a factory test be witnessed?
- How are open FAT items tracked to closure on site?
On-site responsibilities: manufacturer, contractor, owner
- Who handles rigging, utility hookup, classified electrical work and leak testing?
- What does operator training cover, and who signs the training record?
The building trades, including electrical, HVAC and rigging, belong to your contractors. MACH designs extraction equipment and lab layouts. We are not a general contractor, and your licensed trades perform the electrical and construction work. Drawing that line early keeps the install sequence clean.
Frequently asked questions
What is the difference between installation and commissioning?
Installation places the extraction system and connects it to utilities as drawn. Commissioning proves, with a written record, that the installed system runs, alarms and shuts down as designed before any production material goes in.
Does extraction equipment need an engineer's inspection before it runs?
Yes, where the fire code official requires it. Under the International Fire Code, the engineer of record inspects the installed extraction equipment before operation and reports findings before the extraction process is approved. The report includes the serial number and confirms that the model and type match the technical report. Ask your AHJ whether the requirement applies to your project.
What is the difference between FAT and SAT?
FAT tests the system at the manufacturer's facility, before shipment, against the agreed specification. SAT tests the installed system on site against real field signals. It repeats interlock tests under site conditions and closes any punch items carried over from FAT.
Do I need IQ, OQ and PQ for an extraction system?
You need IQ, OQ and PQ if your operation works under GMP expectations or your quality system requires formal qualification. Operations outside that scope typically rely on documented commissioning instead. If you do need qualification, write a URS before purchase and reuse your FAT and SAT records as baseline evidence.
What happens if I change solvents after approval?
A solvent change can send the system back through review, because the approval covers the equipment for its specific use. In Oklahoma City, fire department policy states that modifying the equipment or relocating it voids the approval. Check your own AHJ's rules before you change anything.
Plan the install with the team that built the system
MACH builds turnkey extraction systems and provides complete lab design. Our support covers installation, operator training and on-demand technical support. If you are sequencing an install, start with our turnkey extraction systems or talk to our engineering team. If you'd rather walk through your approval path and site readiness by phone, you can also call our engineering team.